Public Works Project Report: Summer 2019

Excavator

The Public Works Department has completed our general maintenance work of ditching, shouldering and culvert replacements on the following streets: US Rt 1N, Desert Rd., Becks Ln., Baker Rd. (from Rt 125 to end of Cedar Ln.), Ledgewood Ln., Ware Rd., Buttercup Dr., Old County Rd., Sequoia Dr., Pleasant Hill Rd., Grant Rd. and Brown Rd.

The following streets were paved this past season, in addition to ditch, shoulder & culvert replacements: Baker Rd. (from Cedar Ln. to the end of the Town line), Carriage Rd., Poland Rd., Gay Dr., Pratt St., Percy St. and Richards Ln.

Our construction work for the 2019 season has come to an end and we are preparing our trucks for the upcoming plow season. As always, the Public Works Department appreciates the public's patience & understanding during the construction season!